Taiwan ordered 66 F-16Vs. The full order slipped past 2026.
Taiwan’s Defence Ministry said production-line relocations and disruptions pushed the expected delivery of all 66 F-16Vs beyond the original end-2026 plan. Contractors were working two shifts, while some HIMARS deliveries were running ahead of schedule.

Taiwan had ordered 66 new fighters. By November 2025, the problem was not whether the purchase had been approved. It was whether the production line could deliver on the promised timetable.
Reuters reported on 3 November 2025 that the United States was working overtime to speed up delayed F-16V deliveries to Taiwan. In a report to lawmakers, Taiwan’s Defence Ministry said all 66 aircraft, initially expected by the end of 2026, had been pushed back because of production-line relocations and disruptions.
The report did not describe one missing component or one failed test. It identified changes and interruptions in the production line. Taiwan’s Defence Minister Wellington Koo said the United States and Taiwan were working on the delay, while the ministry said contractors were operating two shifts lasting 20 hours a day to accelerate production. Taiwan would monitor progress against the contractual obligations.
Koo said 50 of the Lockheed Martin aircraft were already on the production line. Ten of those were expected to undergo flight tests in the year of the report and to be delivered in 2026. That statement does not mean that all 50 aircraft were complete, accepted or ready for Taiwanese service. It describes a production position inside a larger delivery programme.
The report is more precise than the phrase delayed fighters might suggest. It gives the original end-2026 expectation and says the full set of 66 was pushed back, but it does not give one replacement date for all aircraft. Nor does it say how many jets would arrive after which milestone, how many had already been accepted, or whether the revised schedule would change again.
The F-16 delay was part of a wider delivery picture. Taiwan’s ministry said 24 MK-48 torpedoes and four dummy torpedoes, bought for T$5.46 billion, had also slipped from an expected 2026 delivery to a window between 2026 and 2028. It attributed that delay to production-line disruption. Those torpedoes are a separate purchase, not part of the F-16 quantity.
The ministry also reported delays to Raytheon AGM-154C Joint Standoff glide bombs. They had been expected by the end of 2026 and were instead expected from 2027 to 2028 because of supply-chain problems. The report gave their price as T$135.97 billion. Reuters recorded the ministry’s account and said Raytheon did not immediately respond to a request for comment.
Not every delivery was late. Taiwan said 29 High Mobility Artillery Rocket Systems, or HIMARS, were ahead of schedule. The 18 systems still outstanding were expected in the fourth quarter of 2026 rather than in 2027. That counterexample matters. The record describes uneven delivery performance, not a total collapse of US support or a universal production failure.
Taiwan’s security context made the calendar politically important. Reuters described the island as facing a rising military threat from Beijing and as repeatedly complaining about delays in US weapons ordered through its most important international arms supplier. The report does not identify a particular incident that caused the urgency, and it does not translate the delay into a number of unavailable sorties or a quantified readiness gap.
The practical distinction is still straightforward. A fighter contributes to a force only after production, testing, acceptance, training and the associated support arrangements. Before those steps, an approved order is a future capability. The sources do not establish which of those later steps Taiwan had completed for any particular F-16V, so this account stops at the documented production and delivery delay.
The acceleration effort also has limits that the report leaves open. Working longer shifts may help recover time, but the source does not say whether it changed the final schedule. It does not establish whether the work created trade-offs in quality assurance, flight testing, spares or delivery slots for other customers. Those are plausible questions, not reported outcomes.